5.12 Constructions in progress consist of :
(Unit : Million Baht)
Consolidated and separate financial statements
Constructions in progress
PEA capital Partially funded Funded by interest Total
budget by electricity from electricity
users usage guarantee
As at January 1, 2016 27,874.73 4,718.61 0.55 32,593.89
- Additions 15,053.91 6,515.28 - 21,569.19
- Decreases 17,067.75 6,110.90 0.47 23,179.12
As at December 31, 2016 25,860.89 5,122.99 0.08 30,983.96
(Unit : Million Baht)
Consolidated and separate financial statements
Constructions in progress
PEA capital Partially funded Funded by interest Total
budget by electricity from electricity
users usage guarantee
As at January 1, 2015 27,315.19 5,009.29 - 32,324.48
- Additions 15,683.30 6,590.95 0.56 22,274.81
- Decreases 15,123.76 6,881.63 0.01 22,005.40
As at December 31, 2015 27,874.73 4,718.61 0.55 32,593.89