16 | Modernisation of boiler systems






          Reference: Fleischwaren Sutter GmbH






          In the course of a continuous plant optimisation Sutter decided to introduce an energy management
          system in its main production facility in Gau-Bickelheim. The resulting tax and cost advantages are
          used to compensate the increase in energy costs over the past years. In addition, many tons of CO 2
          emissions are avoided.


          Upon request of the Energy Manager of Sutter, Chris-  In return, the natural gas supplier waived a building
          tian Böhme, the savings potentials had been analysed   cost subsidy for the laying of the gas pipeline. In com-
          and evaluated economically. The process heat supply   parison with the previous fuel oil burners with mecha-
          with three oil-fired steam boilers was quickly identified   nic combined group the new electronically controlled
          as one of the biggest energy consumers of the plant.   burners are able to modulate down to 350 kW and thus
          “Prior to the modernisation we had been supplied with   facilitate a significantly quieter and more efficient
          around 30,000 l of light fuel oil – every week at ano-  part-load operation. In addition, by using a combustion
          ther price. The switch to natural gas has improved our   control with oxygen sensor the losses on the flue gas
          reliability of our energy cost planning. This is an advan-  side could be reduced from 6 % to 5 %.
          tage that we can pass on to our customers in the form
          of stable prices,” explains Christian Böhme.          The availability of spare parts for the boiler control
                                                                based on Siemens Simatic C7 components will fore-
          In the course of the modernisation the dual fuel bur-  seeably become more and more difficult in the coming
          ners had been retrofitted while the existing light fuel   years. Therefore a state-of-the-art boiler control system
          oil supply was maintained as backup. In case of supply   consisting of BCO and SCO was integrated. Besides
          shortages in winter times the natural gas supplier can   the automated water treatment, the SCO includes the
          request the short-term operation with light fuel oil.  adaptive boiler cascade control in order to avoid







































          Sutter’s process heat supply works with greater efficiency after the successful modernisation.
   11   12   13   14   15   16   17   18   19   20