Location : Asoke, New Petchaburi Rd.
                                                                   The Total of project is 319 units

                                                                                  2
        THE ESSE      Asoke                                        GFA : 39,200 m


        (SINC)








         Progress The ESSE (Singha Complex Condominium)

            Commenced on 1 June 2017 and expected to be completed by 30 September
         2019, the ESSE project is a 58-storey building with 177 residential units. Work
         progress as of 31 May 2019:

            Structural work is 100% completed for lift wall, concrete columns
         and slabs, fire escape no. 1 from the 1st floor to the roof, and podium structural
         work. Roof feature construction is 91.5% completed. Architectural work is
         100% completed for masonry wall, 96% completed for plastering work,
         72% completed for ceiling work, and 89% completed for tiling work.

            เริ่มดำเนินการตั้งแตวันที่ 1 มิถุนายน 2560 และคาดวาสิ้นสุดโครงการวันที่ 31 กรกฎาคม
         2562 The ESSE เปนโครงการอาคารสูง 58 ชั้น มีหองพักอาศัย 177 หอง ความคืบหนา
         ของโครงการ ณ วันที่ 31 พฤษภาคม 2562
            งานโครงสรางอาคาร ดำเนินการในสวนของงานพื้นผนังลิฟท, งานเทคอนกรีต
         เสาและงานพื้น, งานเทคอนกรีตบันไดหนีไฟ ตัวที่ 1 ชั้น 1 ถึงหลังคา และงานบันได
         หนีไฟ, งานโครงสรางโพเดียมทั้งหมดเสร็จแลว 100% และในสวนงานโครงเหล็ก
         หลังคาดำเนินการแลว 91.5% งานสถาปตยกรรม ในสวนของงานผนังเสร็จแลว 100%,
         งานฉาบดำเนินการแลว 96%, งานฝาเพดานดำเนินการแลว 72% และงานปูกระเบื้อง
         ดำเนินการแลว 89%