Corporate Performance
Management Discussion and Analysis (MD&A) 1.2 The Major Cities Power System Development
PEA is determined to become a customer-centric Project, Phase 1, had the objective of creating power
organization by placing importance on building and system security, reliability and reducing problems and
managing customer relationships to meet needs and obstacles in maintenance and safety operations.
build satisfaction in addition to increasing the capacity
to deliver services by creating innovations and applying 1.3 The Agriculture Electrifcation Project,
modern technology appropriately. PEA had the following Phase 2, had the objective of expanding electricity
signifcant management and development of operations : services to agricultural areas, plantation and agricultural
gardens in order to support agricultural occupations and
1. Power Systems develop grass roots economic strength.
With consistent investment plans at present and
over the next three years, PEA has prepared plans for 1.4 The New Rural Household Electrifcation
concurrence with predictions of power needs due to the Project, had the objective of expanding power areas to
growing severity of energy and environmental crises, households without power for every household to have
while national development requires energy as a vital electricity in line with government policies.
basic factor. Thus, in addition to providing quality and
effective electricity services, PEA aims to develop power 1.5 The Remote Rulal Household Electrifcation
grids to be strong, smart and secure to become major Project, had the objective of expanding power areas
drivers of PEA’s Smart Grid development by supporting to households in remote areas have electricity in line with
clean energy, reductions in carbon dioxide emissions, government policies.
adjusting power needs for conservation with ability to
access services and receive satisfaction from power 1.6 The Transmission and Distribution
users. Nevertheless, in 2016, PEA continually carried Development Project, Phase 1, had the objective of
out projects related to power system development in developing power systems to suffciently support higher
line with current and future investment plans consisting power needs, increase power system effciency, security
of the following : and reliability while also reducing operation and
maintenance problems, losses in the distribution and
1.1 The Transmission System and Substation increase power system security.
Development Project, Phase 9, had the objective of
developing power systems and adding power distribution 1.7 Distribution System Dispatching Center
stations with ability to suffciently distribute power with Improvement Project, had the objective of enhancing
security, reliability and capacity to support higher power the effciency and management of main communication
needs. systems of PEA, including integrating with systems such
as the Outage Management System, the Geographic
Information System, Automatic Meter Reading, and
supporting connections to Distributed Generation.